Feb 26, 2025 | Approved by Governor on February 25, 2025 | 590 | |
Feb 21, 2025 | Presented to Governor on February 21, 2025 | 564 | |
Feb 21, 2025 | President/Speaker signed | 563 | |
Feb 21, 2025 | Passed on Final Reading with Emergency Clause 48-0-1 | 552 | Vote |
Feb 21, 2025 | Dispensing of reading at large approved | 552 | |
Feb 19, 2025 | Placed on Final Reading | 529 | |
Feb 13, 2025 | Advanced to Enrollment and Review for Engrossment | 506 | |
Feb 13, 2025 | DeKay AM215 adopted | 506 | Vote |
Feb 13, 2025 | Enrollment and Review ER1 adopted | 506 | |
Feb 12, 2025 | DeKay AM215 filed | 494 | |
Feb 04, 2025 | Enrollment and Review ER1 filed | 412 | |
Feb 04, 2025 | Placed on Select File with ER1 | 412 | |
Jan 30, 2025 | Advanced to Enrollment and Review Initial | 386 | Vote |
Jan 30, 2025 | DeKay AM11 withdrawn | 386 | |
Jan 30, 2025 | Natural Resources AM43 adopted | 385 | Vote |
Jan 27, 2025 | Natural Resources AM43 filed | 353 | |
Jan 27, 2025 | Placed on General File with AM43 | 353 | |
Jan 22, 2025 | DeKay AM11 filed | 320 | |
Jan 15, 2025 | Notice of hearing for January 22, 2025 | 187 | |
Jan 13, 2025 | Referred to Natural Resources Committee | 112 | |
Jan 09, 2025 | Date of introduction | 60 |