Nebraska Uniform Commercial Code 4-109

UCC 4-109

4-109.

Delays.

(a) Unless otherwise instructed, a collecting bank in a good faith effort to secure payment of a specific item drawn on a payor other than a bank, and with or without the approval of any person involved, may waive, modify, or extend time limits imposed or permitted by the Uniform Commercial Code for a period not exceeding two additional banking days without discharge of drawers or indorsers or liability to its transferor or a prior party.

(b) Delay by a collecting bank or payor bank beyond time limits prescribed or permitted by the code or by instructions is excused if (i) the delay is caused by interruption of communication or computer facilities, suspension of payments by another bank, war, emergency conditions, failure of equipment, or other circumstances beyond the control of the bank and (ii) the bank exercises such diligence as the circumstances require.

Annotations

  • Efforts of payor bank to effect setoff on settled item held not to constitute "good faith effort to collect" within meaning of former section 4-108. Berman v. United States Nat. Bank, 197 Neb. 268, 249 N.W.2d 187 (1976).