Nebraska Revised Statute 31-913
Chapter 31
31-913.
Drainage improvements; work completed; payment.
Payment for the work done under the provisions of section 31-912 shall be made monthly upon progress certificate of the engineer with ten percent of each estimate to be withheld until final completion and acceptance of said improvement.
Source
- Laws 1959, c. 132, § 13, p. 489.