A public body has discretion to award the contract to one other than the lowest of the responsible bidders whenever a submitted bid contains a relevant advantage. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
By mandating that contracts be awarded to the lowest responsible bidder, the Nebraska Legislature is seeking to protect taxpayers, prevent favoritism and fraud, and increase competition in the bidding process by placing bidders on equal footing. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
Determining the lowest responsible bidder is a two-step process. The first step is for the public body to determine which bidders are responsible to perform the contract. The second step focuses on which of the responsible bidders has submitted the lowest bid. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
Determining the responsibility of bidders is a job for elected officials, and a court's only role is to review those decisions to make sure the public officials did not act arbitrarily, or from favoritism, ill will, or fraud. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
In addition to a bidder's pecuniary ability, responsibility pertains to a bidder's ability and capacity to carry on the work, the bidder's equipment and facilities, the bidder's promptness, the quality of work previously done by him or her, the bidder's suitability to the particular task, and such other qualities as are found necessary to consider in order to determine whether or not, if awarded the contract, he or she could perform it strictly in accordance with its terms. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
Public bodies do not act ministerially only, but exercise an official discretion when passing upon the question of the responsibility of bidders. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
When responsible bidders submit identical bids, the public body must award the contract to the lowest of the responsible bidders. Rath v. City of Sutton, 267 Neb. 265, 673 N.W.2d 869 (2004).
Engineer's estimate of cost of improvements must be stated in notice. Hutton v. Village of Cairo, 159 Neb. 342, 66 N.W.2d 820 (1954).