76-2321. Excavation; notice; contents; commencement.

(1) A person shall not commence any excavation without first giving notice to every operator. An excavator's notice to the center shall be deemed notice to all operators. An excavator's notice to operators shall be ineffective for purposes of this subsection unless given to the center. Notice to the center shall be given at least two full business days, but no more than ten business days, before commencing the excavation, except notice may be given more than ten business days in advance when the excavation is a road construction, widening, repair, or grading project provided for in sections 70-311 to 70-313 and 86-708 to 86-710. An excavator may commence work before the elapse of two full business days when (a) notice to the center has been given as provided by this subsection and (b) all the affected operators have notified the excavator that the location of all the affected operator's underground facilities have been marked or that the operators have no underground facilities in the location of the proposed excavation.

(2) The notice required pursuant to subsection (1) of this section shall include (a) the name and telephone number of the person making the notification, (b) the name, address, and telephone number of the excavator, (c) the location of the area of the proposed excavation, including the range, township, section, and quarter section, unless the area is within the corporate limits of a city or village, in which case the location may be by street address, (d) the date and time excavation is scheduled to commence, (e) the depth of excavation, (f) the type and extent of excavation being planned, including whether the excavation involves tunneling or horizontal boring, and (g) whether the use of explosives is anticipated.

Source:Laws 1994, LB 421, § 21; Laws 2002, LB 1105, § 496.

Annotations

76-2322. Excavator; notice to center.

An excavator shall serve notice of intent to excavate upon the center by submitting a locate request using a method provided by the center. The center shall inform the excavator of all operators to whom such notice will be transmitted and shall promptly transmit such notice to every operator having an underground facility in the area of intended excavation. The notice shall be transmitted to operators and excavators as a ticket. The center shall assign an identification number to each notice received, which number shall be evidenced on the ticket.

Source:Laws 1994, LB 421, § 22; Laws 2014, LB736, § 1; Laws 2019, LB462, § 12.
76-2323. Underground facilities; mark or identify; excavator; violations.

(1) Upon receipt of the information contained in the notice pursuant to section 76-2321, an operator shall advise the excavator of the approximate location of underground facilities in the area of the proposed excavation by marking or identifying the location of the underground facilities with stakes, flags, paint, or any other clearly identifiable marking or reference point and shall indicate if the underground facilities are subject to section 76-2331. The location of the underground facility given by the operator shall be within a strip of land eighteen inches on either side of the marking or identification plus one-half of the width of the underground facility. If in the opinion of the operator the precise location of a facility cannot be determined and marked as required, the operator shall provide all pertinent information and field locating assistance to the excavator at a mutually agreed to time. The location shall be marked or identified using color standards prescribed by the center. The operator shall respond no later than two business days after receipt of the information in the notice or at a time mutually agreed to by the parties.

(2) The marking or identification shall be done in a manner that will last for a minimum of five business days on any nonpermanent surface and a minimum of ten business days on any permanent surface. If the excavation will continue for longer than five business days, the operator shall remark or reidentify the location of the underground facility upon the request of the excavator. The request for remarking or reidentification shall be made through the center.

(3)(a) Beginning September 1, 2024, it shall be a violation of the One-Call Notification System Act for an excavator to (i) serve notice of intent to excavate upon the center for an area in which the excavation cannot be reasonably commenced within seventeen calendar days after the excavation start date indicated pursuant to section 76-2321 or (ii) request remarking or reidentification for any area in which the excavation cannot be reasonably commenced or continued within fourteen calendar days after the date remarking or reidentification is completed.

(b) After receiving notice of any alleged violation of this subsection pursuant to subsection (2) of section 76-2325, the excavator shall in its answer describe the circumstances which prevented the commencement or continuation of excavation within the timeframes set forth in this subsection.

(4) An operator who determines that such operator does not have any underground facility located in the area of the proposed excavation shall notify the center of the determination prior to the date of commencement of the excavation, or prior to two full business days after transmittal of the ticket, whichever occurs sooner. All ticket responses made under this subsection shall be transmitted to the operator and excavator by the center.

Source:Laws 1994, LB 421, § 23; Laws 2014, LB930, § 3; Laws 2019, LB462, § 13; Laws 2023, LB683, § 7.