39-2821. Contracts; changes authorized.

A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the contracting agency in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract.

Source:Laws 2016, LB960, § 21; Laws 2019, LB583, § 15; Laws 2022, LB1016, § 10.