Nebraska Revised Statute 31-112

Chapter 31

31-112.

Drainage improvements; compensation and damages for land taken or affected; application; when made.

At any time before the day set for hearing, after persons are notified as provided in section 31-110, any person or corporation whose lands are taken or affected in any way by the improvement may make application to the commissioners in writing for compensation and damages, and a failure to make such application shall be held a waiver of all rights thereto.

Source

  • Laws 1881, c. 51, § 12, p. 240;
  • Laws 1911, c. 140, § 12, p. 457;
  • R.S.1913, § 1729;
  • C.S.1922, § 1676;
  • C.S.1929, § 31-112;
  • R.S.1943, § 31-112.

Annotations

  • Persons whose land will be damaged by construction of ditch must be compensated. Costello v. Colfax County, 112 Neb. 40, 198 N.W. 357 (1924).

  • Filing of claim waives irregularities in proceedings. Gutschow v. Washington County, 74 Neb. 794, 105 N.W. 548 (1905).